DIYConcreteCurbing.com is supported by readers and may earn an affiliate commission.

Rather have a pro do it for you?

How to Dig for Concrete Curbing

Master the Art of Digging for Concrete Curbing with These Simple Tips

Digging for concrete curbing is an essential step in the process of installing concrete curbs. Properly digging the trench ensures that the curbing will be level, stable, and long-lasting. Here is a step-by-step guide to digging for concrete curbing:

1. Mark the location of the curbing: Use spray paint or stakes and string to mark the location of the curbing. Make sure the line is straight and follows the desired path.

2. Determine the depth of the trench: The depth of the trench will depend on the height of the curbing and the thickness of the base. Typically, the trench should be 1-2 inches deeper than the height of the curbing and the base should be at least 4 inches thick.

3. Excavate the trench: Use a shovel, pickaxe, or excavator to remove the soil from the trench. Start at one end of the line and work your way to the other end. Make sure the trench is wide enough to accommodate the width of the curbing and the base.

4. Check the depth and width of the trench: Use a tape measure or level to check the depth and width of the trench. Adjust as necessary to ensure the trench is the correct size and shape.

5. Compact the base: Use a plate compactor or hand tamper to compact the soil in the bottom of the trench. This will help create a stable base for the curbing.

6. Add gravel or crushed stone: For added stability, add a layer of gravel or crushed stone to the bottom of the trench. This will also help with drainage.

7. Install reinforcement: If necessary, install steel reinforcement in the trench. This will add strength to the curbing and prevent cracking.

8. Pour concrete: Pour concrete into the trench, making sure it is level with the top of the trench. Use a trowel to smooth the surface of the concrete.

9. Finish the surface: Use a broom or other texturing tool to create a non-slip surface on the top of the curbing.

10. Allow the concrete to cure: Allow the concrete to cure for at least 24 hours before removing any forms or backfilling the trench.

By following these steps, you can ensure that your concrete curbing will be level, stable, and long-lasting.